Compost Station Foundation Completed and Ready for Next Stage

The masons have completed work on the compost station foundation. The cement footer for the structure was followed by two rows of cinder blocks. On top of the cinder blocks, the masons attached two inch thick wood boards that will be used when they start the next phase. The wood boards will allow them to nail into place the wood support beams for the roof. It will also allow for chicken wire to be attached to the structure. Instead of cinder blocks or wooden walls, chicken wire will be used to prevent people from removing things from the structure when it is not open for use. The next step of the building process is to install the support beams and the buildings roof. Once that has been done, the chicken wire will be installed and then the floor poured.

Wood boards have been installed over top of the cinderblock foundation in preparation for the next phase of construction
The masons installed two cement boxes which would be used to store egg shells and ash from the stoves